Peace Arch Hospital
Maternity RenovationDaily Activity on Job Site - Wed September 8, 2010
![]() |
| sunny |
![]() |
| 18ºC |
GENERAL REPORT: dry wall continuing
Completed by: Ron Stevenson
ELECTRICAL REPORT: pot light rough in,. conduit install and some wiring install
Completed by: Ron Stevenson
| conduit & wiring installation | new mechanical duct work | drywall install |