Peace Arch Hospital
Maternity RenovationDaily Activity on Job Site - Tue June 29, 2010
![]() |
| sunny |
![]() |
| 17ºC |
GENERAL REPORT: floor laying continuing, patient toilets being installed, millwork install continuing
ELECTRICAL REPORT: nurse call install continuing
MECHANICAL REPORT: Fire alarm verification, GE on site. Sprinkler shutdown, sprinkler head relocation and domestic hot and cold water main tie ins to the 3rd fl mechanical room.