Peace Arch Hospital
Maternity RenovationDaily Activity on Job Site - Wed June 16, 2010
![]() |
| cloudy |
![]() |
| 12ºC |
GENERAL REPORT: painting continuing, plus dry wall mudding and sanding in various areas
ELECTRICAL REPORT: electrical contractor starting to install door controls/card swipe on door into panda infant control stores
MECHANICAL REPORT: Medical Gas Shutdown for 3rd floor tie-in to existing mains.