Daily Activity on Job Site - Tue June 1, 2010

rain
 
12ºC

GENERAL REPORT: lin k hallway 3rd floor hoarding going up so work can be done in and around this area
ELECTRICAL REPORT: houle electric on site continuing network cabling
MECHANICAL REPORT: Sprinkler shutdown 3rd floor link and link radiation system drained.