Peace Arch Hospital
Maternity RenovationDaily Activity on Job Site - Fri August 27, 2010
![]() |
| cloudy |
![]() |
| 14ºC |
GENERAL REPORT: work progessing; most of the walls complete, medical gases piping, electrical moving along.
ELECTRICAL REPORT: conduit work progressing in all the rooms.
Completed by Wes Cooper
| room reference ground main pull box room 5 |