Daily Activity on Job Site - Tue August 24, 2010

sunny
 
20ºC

GENERAL REPORT: steel stud framing, insulation removal, more general demo work
Completed by: Ron Stevenson
ELECTRICAL REPORT: conduit and electrical boxes being installed
Completed by: Ron Stevenson