Peace Arch Hospital
Maternity RenovationDaily Activity on Job Site - Wed August 18, 2010
![]() |
| sunny |
![]() |
| 18ºC |
GENERAL REPORT: Steel stud framing installing, exterior fin removal continuing
Completed by: Ron Stevenson
ELECTRICAL REPORT: patient reference ground cable and boxes being installed
Completed by: Ron Stevenson
| Exterior concrete fin removal | Exterior concrete fin removal | ceiling brackets for steel studs | steel stud install |
| steel stud install |