Daily Activity on Job Site - Mon August 16, 2010

sunny
 
28ºC

GENERAL REPORT: Steel track for walls in rooms 6 & 7 being installed
Completed by: Wes Cooper
ELECTRICAL REPORT: prep work for conduit in room 5
Completed by: Wes Cooper



Preparation in PARR for 3rd fl reno ph2 demolition